News

2011 Expansion UPDATE 10-8-12

Work is continuing on the water line expansion at 54th & Leedy.  Progress has been slow due to the large amount of rock encountered and the amount of trees and brush that needed removed.  We hope to have all the line in and meters installed by the end of November. 

News

2011 Expansion Update - 54th Street

The line expansion work began on 8/29/12 at 54th & Jennings and will continue towards Leedy.  When this project is complete there will be 8 new customers added.  The work is expected to take 3 to 4 weeks. 

News

2011 Expansion Update - 54th Street

The line expansion work began on 8/29/12 at 54th & Jennings and will continue towards Leedy.  When this project is complete there will be 8 new customers added.  The work is expected to take 3 to 4 weeks. 

News

URGENT Information 8/24/12

 

Dear Customer,
 
Denison State Bank has informed us they will no longer be accepting customer water payments at their bank branches. They will stop taking water customer payments on September 30, 2012.
News

URGENT Information 8/24/12

 

Dear Customer,
 
Denison State Bank has informed us they will no longer be accepting customer water payments at their bank branches. They will stop taking water customer payments on September 30, 2012.
RSS
First2425262729313233Last

Theme picker