All of the water lines in the 86th street expansion area have been installed and the creek crossing completed. We are in the process of pressure testing the line to make sure there are no leaks. The line will then be cleaned and water sample tests sent to the State for testing. Once the tests results are back and they are good, the individual meters will then be installed. Hopefully by the end of June we will have some of the 10 meters in this area installed and they will be ready for the water line to be ran from the meter to the residence. If you have any questions feel free to contact the office, 785-986-6913.